Date Asked: 01/09/2018 Date Answered: 01/10/2018
Poster: ANTHONY POMPEI Company: RIDOT
Question:
There is a discrepancy between the revised Substantial Completion date as shown on Page JS-14 of the Job Specifics posted as part of Addendum No. 8 and the date shown in the Quest bid file. Please confirm the correct Substantial Completion date.
Answer:
The Substantial Completion date for this project is August 17, 2019 as shown on Page JS-14 in Addendum No. 8.
Date Asked: 01/02/2018 Date Answered: 01/03/2018
Poster: paul grimaldi Company: J. F. WHITE CONTRACTING CO.
Question:
please reference---JS-PAGE 86----MATERIALS : the specification states-- " Each bidder is required to identify their intended isolation system supplier at the time of bid "-----please clarify this statement
Answer:
The sentence referred to will be removed as part of Addendum 8.
Date Asked: 12/28/2017 Date Answered: 12/29/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
item 926.9901 - temporary impact attenuator states that attenuators used shall be or a max. design speed of 70 mph. please clarify that this is correct since this requirment is not standard for a temporary impact attentuator. The specs also state that a 55 mph will be required for horton farm road, 45 mph for the crossovers and 70 mph for all other statges. Three types of attenttuators are needed but the DOQ only call for 2 each. Please clarify.
Answer:
The reference to 70 mph will be removed from Item 926.9901 and replaced with a NCHRP 350 Test Level 3 rating requirement. This change will be incorporated as part of Addendum No. 7.
Date Asked: 12/28/2017 Date Answered: 12/29/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
The plans show shock absorbing barrels but the pay item (926.9901) is for temporary impact attentuators. Please clarify that shock absorbing barrels are acceptable for this project.
Answer:
Yes, shock absorbing barrels are acceptable for this project provided they meet the requirements set forth in the specifications and do not impede on the traffic lanes.
Date Asked: 12/22/2017 Date Answered: 12/27/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
The quantity for Item No. L01.0104 is 260 SY but item No. L02.0101 is 1050 SY. Please clarify why the quantities differ.
Answer:
The contract quantity for Item Code L01.0104 will be revised by Addendum No. 7.
Date Asked: 12/22/2017 Date Answered: 12/22/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
There is no min. bid for item 212.2000 in quest lite.
Answer:
This item has been revised to include a minimum acceptable bid price. This revision is incorporated as part of Addendum No. 7.
Date Asked: 12/22/2017 Date Answered: 12/27/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
CODE 800.9904 STATES THAT ELECTRICAL CONDUIT, PULL BOXES ARE INCLUDED IN THE ITEM BUT THE CONTRACT INCLUDES PAY ITEMS FOR PULL BOXES AND CONDUIT IN STRUCTURE. PLEASE CLARIFY HOW THE ITEMS ARE PAID FOR.
Answer:
Item Code T05.0320 “PULL BOX ON STRUCTURE TYPE V STANDARD 18.6.3” are for pull boxes along I-195 as indicated in the Distribution of Quantities. The pull boxes in the bridge barrier under Item Code 800.9940 are for the bridge substructure Lump Sum only.
Date Asked: 12/21/2017 Date Answered: 12/27/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
PLEASE CLARIFY THE ALLOWED TIMES FOR STAGES 1D / 2D. THE TMP STATES THAT 2 LANES CAN ONLY BE TAKEN DURING 8 PM TO 6 AM. IF THE STRUCTURAL STEEL IS NOT INSTALLED IN ONE NIGHT WHICH DOES NOT SEEM POSSIBLE, DOES THE BARRIER NEED TO BE MOVED TOWARDS THE MEDIAN AND RESET THE FOLLOWING NIGHT. IS IT THE DEPARTMENT INTENTIONS THAT THE BARRIER WILL BE MOVED EVERY NIGHT UNTIL THE STEEL IS INSTALLED. THERE SEEEMS TO BE NOT ENOUGH TIME TO SET UP THE BARRIER, INSTALL THE STEEL, REMOVE BARRIER AND RESTORE THREE LANES IN ONE NIGHT FOR BOTH BOUNDS. ALSO THE REMOVE AND RESET BARRIER ITEM DOES NOT TAKE INTO ACCOUNT ALL THE MOVES.
Answer:
It is should be understood that multiple nights are expected to be required to install the superstructure steel. Steel placement and barrier movement need not occur for both bounds during the same night. Typical lane closures for a single bound may be performed with barrels and/or cones per MUTCD requirements if feasible based on the required crane and steel erection submittals to be developed and submitted by the contractor.
Date Asked: 12/21/2017 Date Answered: 12/22/2017
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Please review quantity for Item 601.0200 Class XX Concrete. The quantity seems to be very high.
Answer:
The concrete is to be used to lock in both the proposed barriers and the proposed curb. No change to the quantity is required.
Date Asked: 12/20/2017 Date Answered: 12/27/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
sheet 9 states to demo and install superstructure during night time hours. Should it not say during weekend cross overs. Please clarify.
Answer:
Demolition shall occur during weekend crossovers, 24 hours per day per TMP Attachment A as reissued in Addendum No. 3. Superstructure installation shall occur using Stage D traffic control setup per the Maintenance and Protection of Traffic Plans that were reissued in Addendum No.3. The installation of the superstructure may occur on any day during the permitted hours in accordance with the TMP Attachment A.
Date Asked: 12/19/2017 Date Answered: 12/22/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
CODE 828.9902 ELEASTOMERIC BEARINGS ARE INCLUED ON THE JS PAGES BUT THE BEARINGS WERE ELIMINATED FROM THE PLANS.
Answer:
As stated in Addendum No. 5, please remove pages JS-92 and JS-93 which will result in deleting the specifications for the elastomeric bearings. The index for the Job Specific Specifications was also updated as part of this addendum to account for the removal of this section.
Date Asked: 12/19/2017 Date Answered: 12/22/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
THE ULTRA HIGH PERFORMANCE SPEC IS STILL INCLUDED IN THE JS PAGES BUT WAS REMOVED FROM THE PLANS.
Answer:
As stated in Addendum No. 5, please remove pages JS-74 thru JS-81 which will result in deleting the specifications for the ultra-high performance concrete. The index for the Job Specific Specifications was also updated as part of this addendum to account for the removal of this section.
Date Asked: 12/19/2017 Date Answered: 12/27/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
IS THE GEOTECH REPORT BY PAUL ALIDINGER DATED 2/12 AVAILABLE?
Answer:
Yes, this report will be provided "For Information Only" separate from the bid documents as supplemental information and will be available for pickup on CD as of 12:00PM today (12/27) at 2 Capitol Hill in Room 260.
Date Asked: 12/19/2017 Date Answered: 12/27/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
PLEASE CLARIFY THAT SECTION 11 ON PAGE CS-14 STILL APPLIES TO THIS PROJECT SINCE PRECAST PANELS ARE NOT BEING USED. ALSO CLARIFY THAT A CONTRACT BOND IS REQUIRED BY THE STEEL FABRICATORS?
Answer:
This specification will be revised as part of Addendum No. 7.
Date Asked: 12/19/2017 Date Answered: 12/27/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
CS-8 STATES THAT THE "CONTRACTOR SHALL FURNISH THE ENGINEER WITH TIME LAPSE HIGH END IMAGING DOCUMENTING ALL OF THE CONSTRUCTION ACTIVITIES STATING WITH STAGE 1 DEMO AND ENDING WITH THE COMPLETION OF MILESTONE #2" HOW IS THIS PAID FOR?
Answer:
The work to view and record the project construction as indicated above is paid for under Item Code T12.9901 “MOBILE CAMERA SURVEILLANCE SYSTEM”. This specification will be revised by addendum No. 7.
Date Asked: 12/19/2017 Date Answered: 12/27/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
PER ADDENDUM NO. 5, PLEASE CONFIRM THAT NO BEARING PEDESTALS ARE REQUIRED SINCE SHEET 5 UNDER MATERIALS STILL REFERENCE BEARING PEDESTALS.
Answer:
Correct, no bearing pedestals are required. Height adjustments beneath the bearings will be accomplished by using a lower bearing plate/shim to be installed by manufacturer and shallow grout pads beneath the masonry plates that are less than 1 inch. Further clarification will be provided by addendum No. 7.
Date Asked: 12/19/2017 Date Answered: 12/22/2017
Poster: paul grimaldi Company: J. F. WHITE CONTRACTING CO.
Question:
please confirm-pay item-122--943.0200---TRAINEE MAN-HOURS -- does not have a minimum acceptable bid price
Answer:
The unit price for this item will be revised to include a minimum acceptable bid price. This change will be issued as part of Addendum No. 7.
Date Asked: 12/18/2017 Date Answered: 12/29/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Since the addendums removed the accelerated portions of the bridge (precast items) and the bridge is conventional construction, how does the desincentives and incentives apply to the project? Has the Department performed a time determination without ABC to see if the completion date can be met?
Answer:
The project is still considered ABC due to the limited time constraint for completion. The incentive / dis-incentive still apply per the JS specifications accordingly. The precast items are not necessary to achieve the required substantial completion date. Due to the extended advertising time for this contract, the contract milestone dates will be extended accordingly as part of Addendum No. 8. Addendum No. 7 will postpone the bid opening until 1/17/18 to provide time to account for these changes.
Date Asked: 11/30/2017 Date Answered: 12/04/2017
Poster: Joe Colapietro Company: Cardi Corporation
Question:
The revised job specific for 704.9901 and 704.9903 has stated a minimum depth of 26" is required. You cannot provide the depths of inverts, or what each specific structure will take for a repair. Please adjust this item from paid for by each to paid for by Vertical Linear Foot, or add a separate item to make repairs beyond the minimum 26" depth that will be paid for by the vertical linear foot. You have not provided sufficient information to properly bid any of the repair structure items. Please advise how we should proceed with items 704.9901, 704.9902, 704.9903, 704.9904, 704.9905.
Answer:
In addition to the each item for the minimum repairs, two items for vertical foot repairs will be added to the contract for use at locations where the required repairs extend beyond the 26" minimum as determined by the Engineer. These items will be added in the next addendum.
Date Asked: 11/29/2017 Date Answered: 12/01/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
On sheet 44, 45 and 46, the plan view shows the anchor bolts at 1" diameter, but the elevation view at 1 1/4" diameter and 1 1/2" diameter. Please clarify which is correct size.
Answer:
The anchor bolt size will be clarified as part of the next addendum.
Date Asked: 11/28/2017 Date Answered: 12/01/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
ITEM NO. 79 - GUARDRAIL ANCHORAGE TRAILING END SECTION STD 34.3.4. THIS ITEM IS LISTED AS AN ONLY ACCEPTABLE BID PRICE OF $2000 PER EACH IN THE QUEST LITE PROGRAM. PLEASE CLARIFY.
Answer:
The bid price will be fixed for the next addendum to not be set as the only acceptable bid price.
Date Asked: 11/28/2017 Date Answered: 12/01/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
DOQ FOR ITEM NO. 926.0120 - ANCHORED BARRIER STATES 1854 LF. THE PLANS SHOW APPROX. 500 LF. PLEASE CLARIFY WHERE THE ADDITIONAL FOOTAGE IS LOCATED.
Answer:
The quantity for this item will be revised in the next addendum. The quantity is based on the total length of the barrier as shown on the plans for 2 phases.
Date Asked: 11/27/2017 Date Answered: 11/28/2017
Poster: paul grimaldi Company: J. F. WHITE CONTRACTING CO.
Question:
The posted Addendum 3, PDF, does not include the Revised Volume 2 , Contract Drawings. ( 12 ea. )-----please issue these revised drawings.
Answer:
The sheets in question will be included in the next addendum.
Date Asked: 11/22/2017 Date Answered: 11/29/2017
Poster: Peter Calcagni Company: Manafort Brothers Inc
Question:
Type your questions here. Will there be a job specific added for 708.9901, 708.9902 and 708.9905? If not can you please clarify how the final restoration will be paid for each of these items such as the loam seed and jute mesh or placement of rip rap.
Answer:
A Job Specific item will be created detailing the work required and method of payment via a future addendum.
Date Asked: 11/22/2017 Date Answered: 12/04/2017
Poster: Jeff Patch Company: Atlantic Bridge & Engineering
Question:
Note 2 - Erection of Bridge Components on General Bridge Notes Sheet 3 of 3 indicates that "The capacity of the crane and all lifting connecting devices shall be adequate for 150% of the total pick load including spreaders and other materials." Typically RIDOT requires this factor of safety to be 125% unless the pick is over AMTRAK in which case the factor of safety is 150%. As such, please confirm that a 125% factor of safety can be used for this project as the work does not occur near or over AMTRAK.
Answer:
The 125% requirement is correct. The note in question will be revised by addendum.
Date Asked: 11/22/2017 Date Answered: 11/29/2017
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Will you be providing Job specifics for items 704.9902, 704.9904, 704.9905. Also, if they include repairs to the vertical walls can this be changed as suggested for Items 704.9901 and 704.9903 in a previous question. Since there is no accurate way to estimate how many vertical feet of repairs will need to be made.
Answer:
A Job Specific item will be created detailing the work required and method of payment via a future addendum.
Date Asked: 11/22/2017 Date Answered: 11/29/2017
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Item 704.9901 and 704.9903 call to replace the top course of brick, and also to repoint and repair any deteriorated wall areas. The wall repairs are normally carried under a separate item paid for by the vertical foot. There are no inverts or elevations on the plans, or a basin by basin breakdown of how much repair can be expected. Please adjust this item to reflect the standard of replacing corbels by the each and vertical wall repairs paid by the vertical foot.
Answer:
Additional details showing minimum depth of wall removal expected has been added to clarify this item in Addendum 3. The Job Specific specifications were also modified in Addendum 3. The drainage inverts are not available.
Date Asked: 11/22/2017 Date Answered: 11/29/2017
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Item 703.0008 has no inverts called out on the plans. Please clarify invert elevations as this will change the amount of fine aggregate above the pipe.
Answer:
The drainage inverts are not available. Install top of pipe 4’-0” below the top of pavement at station 90+00 and slope to catch basin at station 91+27 Install in accordance with RI Standard 1.1.0 .
Date Asked: 11/22/2017 Date Answered: 11/29/2017
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Item 703.0008 Calls for 8" perforated concrete pipe. Is there an approved supplier for this? Or should this be a different material?
Answer:
This item will be revised by addendum.
Date Asked: 11/21/2017 Date Answered: 11/22/2017
Poster: Chuck Mercier Company: Manafort Brothers Incorporated
Question:
108.1000, Prosecution and Progress states "The crossover for I-195 Stage 1A demolition shall start no earlier than April 22, 2018 unless otherwise approved by the engineer, to be eligible for the incentive." Does "start" refer to the construction of the crossovers or the use of the crossovers?
Answer:
The "start" date for Stage 1A used to calculate the contractual incentive/ disincentive payments shall be when the crossover on 195 is implemented at the start of demolition activities.
Date Asked: 11/21/2017 Date Answered: 11/29/2017
Poster: Chuck Mercier Company: Manafort Brothers Incorporated
Question:
Can a plan be provided that shows how the maintenance and protection of traffic will be provided for during the construction of the crossovers and during periods when the crossovers are constructed but not in use?
Answer:
Construction of the crossovers will need to occur using standard lane closures within the allowable restrictions of the TMP. The crossovers should not be fully in place without being used.
Date Asked: 11/21/2017 Date Answered: 11/22/2017
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Addendum 1 added a Job Specific for Friction course. There is no bid item, and the pavement structure calls for 12.5mm Modified. Please clarify.
Answer:
The highway plans and DOQ have been modified to clarify this item in Addendum No. 3
Date Asked: 11/21/2017 Date Answered: 11/22/2017
Poster: Phil Bongiovanni Company: Manafort Brothers Incorporated
Question:
Please provide a deck pour sequence.
Answer:
A deck pouring sequence plan and details will be provided by addendum.
Date Asked: 11/21/2017 Date Answered: 12/01/2017
Poster: Joe Colapietro Company: Cardi Corporation
Question:
How is the concrete slab located on the 40.2.1 barrier paid for?
Answer:
The concrete slab as shown in the Standard Item 40.2.1 Single – Faced Precast Median Barrier With Concrete Slab, is included in the payment item per linear foot where applicable.
Date Asked: 11/21/2017 Date Answered: 11/29/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
PLEASE CLARIFY WHERE ITEM NO. 203.0700 PERVIOUS FILL IS BEING USED.
Answer:
This item was removed as part of Addendum No. 3.
Date Asked: 11/21/2017 Date Answered: 11/22/2017
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Item 203.9902 calls out uniaxial and biaxial grid as shown on the plans. Is there any biaxial grid on this project? Sheet 28 of Volume 2 only shows uniaxial grid. Please clarify.
Answer:
Biaxial geogrid is required for this project. Product specific detail information will be added to Job Specific Code 203.9902 by addendum to clarify location of biaxial geogrid.
Date Asked: 11/21/2017 Date Answered: 11/22/2017
Poster: Phil Bongiovanni Company: Manafort Brothers Incorporated
Question:
Addendum 2 Item 11 on JS-48 calls out a longitudinal closure pour. Now that the design has changed to cast-in-place, can we assume using rebar couplers with two pours and eliminate the need for the closure pour?
Answer:
No. The longitudinal closure pour will remain on the plans as shown. The Contractor may, at the approval of the Engineer, propose the alternative described in the question as part of a Value Engineering proposal.
Date Asked: 11/21/2017 Date Answered: 11/22/2017
Poster: Phil Bongiovanni Company: Manafort Brothers Incorporated
Question:
Addendum 2 changed this project to cast-in-place. Will there be a revised shear stud layout?
Answer:
Yes. The shear stud layout will be provided in Addendum No. 3.
Date Asked: 11/21/2017 Date Answered: 11/22/2017
Poster: Phil Bongiovanni Company: Manafort Brothers Incorporated
Question:
Addendum 2 CS-11 Stage 1 - 10th bullet point states "Stage 1C with Rolling Roadblocks. Erect Prefabricated SE Girders (Modular Unit with Side Shielding attached for Installation of Safety Barrier, Individual Girder and Diaphragms) during weekend rolling roadblocks." What is the "Modular Unit with Side Shielding ..."? Also, please detail the parameters of rolling roadblocks.
Answer:
Modular unit used for this purpose indicates two steel girders connected with cross frames as shown on Sheet 35 of 53 in Volume 2. The Sequence of Accelerated Bridge Construction and Schedule on page CS-11 suggests attaching the Side Protection Shielding (Code 803.9903) to the modular girder before erecting it. Further details regarding the rolling roadblocks will be provide in the TMP via addendum.
Date Asked: 11/21/2017 Date Answered: 11/29/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
THE TRAFFIC PLANS DO NOT TAKE ACCOUNT THE REMOVAL OF THE EXISTING MEDIAN BARRIER AND THE PLACEMENT OF THE NEW MEDIAN BARRIER ON I-195. IS THIS WORK REQUIRED TO BE COMPLETED BEHIND TEMPORARY BARRIER OR LANE CLOSURES. IF SO PLEASE PROVIDE TRAFFIC CONTROL PLANS FOR THE REMOVAL OF THE EXISTING MEDIAN BARRIER FOR THE CROSS OVERS AND PLACEMENT OF THE NEW MEDIAN BARRIER ON I-195.
Answer:
Median barrier work is anticipated to be completed with standard lane closures as allowed by MUTCD and the contract documents. Additional methods may be proposed by the contractor provided they comply with the requirements of the TMP.
Date Asked: 11/21/2017 Date Answered: 11/29/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify if a protective coating is applied the abutment beam seats and vertical faces of backwalls as noted on sheet 5 of the drawings. Code 800.9920 does not include the backwalls and abutments seats, it only includes the safety barrier.
Answer:
The protective coating for all substructure elements is included under Item Code 800.9940.
Date Asked: 11/21/2017 Date Answered: 11/29/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify where item no. 201.0420 R & D concrete slab is located.
Answer:
Item 201.0420 is located from I-195 station 121+50 LT/RT to 124+40 LT/RT as broken down in the Distribution of Quantities. This item consists of removing the concrete cap in the median barrier.
Date Asked: 11/20/2017 Date Answered: 11/20/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
How is restoring the mural on the northwest wingwall paid for? Can you provide the original painter for the mural.
Answer:
Additional information will be provided via addendum.
Date Asked: 11/14/2017 Date Answered: 11/17/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
WILL THE DEPARTMENT ALLOW STAY IN PLACE FORMS ON THIS PROJECT?
Answer:
SIP forms will be allowed for this project subject to RIDOT approval of applicable shop drawings.
Date Asked: 11/14/2017 Date Answered: 11/22/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
PAGE CS-41 FROM ADDENDUM NO. 2. PLEASE RE-ISSUE IN COLOR. CAN'T READ.
Answer:
This page is being revised via the next addendum.
Date Asked: 11/13/2017 Date Answered: 11/15/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
PLEASE CLARIFY IF THE SHELFS BEHIND THE EXISTING ABUTMENTS ARE PRECAST OR CAST IN PLACE.
Answer:
See response below regarding precast versus cast-in-place.
Date Asked: 11/13/2017 Date Answered: 11/14/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
DOES THE CONTRACTOR HAVE THE OPTION TO CAST IN PLACE THE PRECAST ELEMENTS?
Answer:
Either option will be acceptable provided all contract requirements, including but not limited to contract completion dates and TMP Restrictions, are met.
Date Asked: 11/08/2017 Date Answered: 11/14/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
CODE 800.9940 STATES THAT PROTECTIVE COASTINGS IS INCLUDED IN THE LUMP SUM ITEM BUT THERE IS AN ITEM FOR CONCRETE SURFACE TREATMENT. PLEASE CLARIFY.
Answer:
Item Code 820.0110 applies for the double faced, single faced and transition precast median barriers along I-195. Item Code 800.9940 applies for the concrete protective coating for the bridge substructure only. Similarly, Item Code 800.9920 applies for the concrete protective coating for the bridge superstructure only.
Date Asked: 10/30/2017 Date Answered: 11/03/2017
Poster: Susan Mathews Company: J.F. White
Question:
Please re-issue Pages 67-83 of Addendum 2 PDF. The downloaded PDF only shows a portion of the drawing on these pages.
Answer:
Please confirm this question was posted to the correct project as Addendum No. 2 contains only 80 pages.
Date Asked: 10/20/2017 Date Answered: 10/20/2017
Poster: paul grimaldi Company: J. F. WHITE CONTRACTING CO.
Question:
considering that there is addendums still to be issued and questions to be answered---could the bid date be postponed 1 week
Answer:
The Bid Opening Date is being revised to Friday, December 1 as part of Addendum No. 2.
Date Asked: 10/19/2017 Date Answered: 11/01/2017
Poster: Dan Kelley Company: Aetna Bridge Company
Question:
Please confirm the $2,000 per hour per travel lane negative assessment in Section 937.1000 will only apply after the contractor has the full bridge open to traffic and is not tied to the Interim Completion Date #1 of 12/7/18.
Answer:
Confirmed. The $2,000 per hour per travel lane negative assessment for All Horton Farm Lanes Open to Traffic will only apply after the contractor has the full bridge open to traffic. This assessment is not tied to the Interim Completion Date #1 of 12/7/18.
Date Asked: 10/19/2017 Date Answered: 10/20/2017
Poster: Dan Kelley Company: Aetna Bridge Company
Question:
Ramp FR-1 detour is allowed during night hours only as needed to progress the work during any stage. Section 937.1000 has a negative assessment of $4,000 per hour after 6 am but at what time will the contractor be allowed to start the detour?
Answer:
The TMP is being revised as part of Addendum No. 2. Closure of Ramp FR-1 will be allowed, with prior approval of the Engineer, from 10PM to 6AM any night of the week.
Date Asked: 10/19/2017 Date Answered: 11/03/2017
Poster: Tracy Dusablon Company: Aetna Bridge Company
Question:
Is it possible to have Volume 1 of the plans resubmitted through an addendum for download? I do not know about others, but after sheet 85 there are major printing issues. The document continues to cycle back and begin again at sheet 85 (ex: prints 85-92, then 85-95, then 85-104...). Even printing the individual sheets is challenging.
Answer:
The issues may be linked to the equipment/software being used to print the files as we are not experiencing printing issues with the files provided on the advertising CD. If printing issues remain, please post an additional question stating so.
Date Asked: 10/19/2017 Date Answered: 10/20/2017
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
DUE TO ALL THE PROJECTS BIDDING. CAN THE DEPARTMENT EXTEND THE BID DATE BY TWO WEEKS?
Answer:
The Bid Opening Date is being revised to Friday, December 1 as part of Addendum No. 2.
Date Asked: 10/19/2017 Date Answered: 12/06/2017
Poster: paul grimaldi Company: J. F. WHITE CONTRACTING CO.
Question:
reference contract drawing sheet no. 58-----note concerning removal and disposal of building vault and electrical equipment-----please provide additional information so that this item may be priced correctly.---also, where is this work paid for ?
Answer:
The building vault and electrical equipment shall not be removed but shall be abandoned. The notes on the plans will be revised via a future addendum.
Date Asked: 10/19/2017 Date Answered: 10/20/2017
Poster: Claudia Montan Company: MIG Corporation, Inc.
Question:
Can you please clarify the Substantial Completion Date for this project? Page JS-14 has it as June 29, 2019 whereas Quest Lite has a date of 11/08/2018.
Answer:
The Substantial Completion Date is correct as written on Page JS-14. Quest will be updated as part of Addendum No. 2.
Date Asked: 10/13/2017 Date Answered: 10/17/2017
Poster: paul grimaldi Company: J. F. WHITE CONTRACTING CO.
Question:
Refence: CS-Section 6--Sequence of Accelerated Bridge Construction and Schedule--pages CS-11 and CS-12 , states that in Stage 1D & 2D erection of prefabricated girders will be at night during weekend crossovers. M.O.T. Drawings sheet 115--stage 1D and sheet 131--stage 2D show 1 lane of travel on 195 West and 1 lane of travel on 195 East during the crossover. TMP--Attachment A--Only allows 1 lane of travel on both 195 West and 195 East on Sunday,Monday and Saturday from Midnight till 6 AM , and outside these times either 2 or 3 lanes in each direction, ---please confirm that on these three days,--- between midnight and 6 AM,--- for stages 1D & 2D,--- the crossover will need to be installed , prefabricated girders erected, and the crossover removed.
Answer:
The sequence descriptions stated in the referenced CS pages and the M.O.T. drawings for installing the crossover, erecting the girders, and removing the crossovers will be revised by addendum to allow for alternative staging setups including rolling roadblocks.