Date Asked: 01/09/2018 | Date Answered: 01/10/2018 |
Poster: Lee Taylor | Company: D'Ambra Const. Co., Inc. |
Question:
Please verify if an MTV will be required for placing the very small quantity of ramp friction course material. |
|
Answer:
A Material Transfer Vehicle (MTV) will not be required on this ramp. |
Date Asked: 01/08/2018 | Date Answered: 01/09/2018 |
Poster: Lee Taylor | Company: D'Ambra Const. Co., Inc. |
Question:
The price adjustment price given for liquid asphalt is $420.00 per ton. The latest other projects bidding are $402.50 to $405.00 per ton for this material. Please verify the correct adjustment price. |
|
Answer:
This project advertised on December 27, 2017. The Liquid Asphalt and Fuel Price Adjustments posted at the time were: Liquid Asphalt: $420.00 per ton; Diesel Fuel: $2.0436 per gallon; Prices effective December 15, 2017. |
Date Asked: 01/08/2018 | Date Answered: 01/09/2018 |
Poster: Lee Taylor | Company: D'Ambra Const. Co., Inc. |
Question:
There is a job specific description for friction course (page JS-4 - JS-6) however no bid item. Where would there be a requirement for this material? |
|
Answer:
The Friction Course is required on the North Smithfield road segment location as listed in Table 1. The Distribution of Quantities was revised in Addendum 1; which should be posted today. |