Date Asked: 06/07/2018 Date Answered: 06/12/2018
Poster: Mike Sarrasin Company: John Rocchio Corporation
Question:
Page JS-8: Substantial Completion: October 2, 2018. Page CS-7:Contract Completion Dates: All work of this contract is to be substantially complete by October 2, 2019.
Answer:
Substantial Completion shall be October 2, 2019. JS-8 revised to October 2, 2019. Revised sheet shall be provided in Addendum No. 1.
Date Asked: 06/07/2018 Date Answered: 06/12/2018
Poster: Mike Sarrasin Company: John Rocchio Corporation
Question:
Bid Item: 067 823.1750 ASPHALTIC EXPANSION JOINT SYSTEM 56 LF. Sheets 46 & 49 show "SAW AND SEAL"
Answer:
Item 823.1750 - ASPHALTIC EXPANSION JOINT SYSTEM has been removed and replaced with item 821.1690 – Saw and Sealing Joints in Bituminous Concrete Pavement. Revised DOQ shall be provided in Addendum No. 1.
Date Asked: 06/07/2018 Date Answered: 06/12/2018
Poster: Mike Sarrasin Company: John Rocchio Corporation
Question:
SHEET 50 TEMPORARY UTILITY BRIDGE shows the bridge as 17' wide. Is there anything else on the bridge other than the 12" water line? Why so wide? Design is by the Contractor.
Answer:
The temporary utility bridge shall be designed and detailed by the contractor. Sheet 50 – Temporary Utility Bridge shows the area available for the temporary bridge and should not be taken as an indication of the size or type of bridge that can or should be used. The temporary bridge is intended to support the temporary water main during construction. The size of the area represents a maximum footprint for all temporary bridge components for planning and permitting purposes. The temporary bridge used is anticipated to be smaller than the maximum footprint shown, though the size is at the contractor’s discretion and per the contractor’s design.
Date Asked: 06/07/2018 Date Answered: 06/12/2018
Poster: Mike Sarrasin Company: John Rocchio Corporation
Question:
SHEET 23: "GAS INSALL DETAIL (TO BE INSTALLED BY BRIDGE CONTRACTORS NATIONAL GRID APPROVED GAS SUB)" There is no Bid Item for gas work by the National Grid Subcontractor.
Answer:
The Gas line shall be installed by a National Grid approved Contractor provided in Appendix C. This work shall be paid for under RIDOT utility force account. Revised sheet shall be provided in Addendum No. 1.
Date Asked: 06/06/2018 Date Answered: 06/12/2018
Poster: Peter Calcagni Company: Manafort Brothers Inc
Question:
The Plans and Specs are asking for a 12.75” OD steel pile casing which is 80 ksi. The 12.75 x 500 wall material is generally available in 45ksi, never 80ksi.Design is by the Subcontractor. Is it possible to allow either of the following as minimum criteria for casing? 11-7/8” OD x .500 min wall in 80ksi. 12-3/4” OD x .500 min wall in 45ksi.
Answer:
The 12-3/4” outside diameter with 0.500” min. wall thickness in 45 ksi is acceptable. Revised sheets and Spec shall be provided in Addendum No. 1.
Date Asked: 06/06/2018 Date Answered: 06/13/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
THE 20% DBE REQUIREMENTS SEEMS HIGH FOR THIS PROJECT.
Answer:
This DBE goal is supported by the available work for DBEs, who are ready, willing and available to perform the work.