Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
JS-27 states that cost for furnishing and installing supplemental steel reinforcement bars and wire mesh shall be included for payment under this item and will not be paid separately. The standard spec states that it will be completed on force account. The reason it was on force account beacause it is difficult to estimate how much rebar or wire mesh is needed until the areas is demolished and exposed. Please reconsider that the rebar is included. If it is included, please provide a quantity the contractor should carry in the bid.
Answer:
An addendum will be prepared to address this issue.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
T16.0300 - Ground Mounted Primary Directional Sign-post Steel Breakway. Please clarify where these posts are located.
Answer:
This Item will be removed by addendum.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
T15.0100 - directional regulatory and warning signs, please clarify where these signs are located. There is no item for temporary tarffic signs.
Answer:
An addendum will be prepared.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify how the paveemnt removal for the joints at bridges 712 ands 713 is paid for. Also after the joint is complete, how is the full depth asphalt pavement is paid for before the bridge is mirco milled and paved.
Answer:
An addendum will provided to address these issues.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
item 401.9902 - pay adjustments. The min. bid is $1 with 1 each quantity for a total of $1. This does not seem to be correct.
Answer:
This is will be addressed by addendum.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
There is no min. bid in quest for the TMA.
Answer:
This issue will be addressed by addendum.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify if shielding is required for the demo of the joints for bridges 712 and 713. If so there is no pay item, no details on the plans, and no details showing the pay limits.
Answer:
Shielding is required in Job Specific 800.9901. An Item will be provided by addendum.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify if rebar is epoxy coated or galvanized. The pay item is epoxy coated.
Answer:
A new Item will be provided by addendum.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
How is the removal of the median at the approaches for Bridges 712 and 713 paid for. The pay items don't include sawcutting, R & D flexible pavement in front of curb and median, earth excavation for gravel under median, new gravel borrow, curb lock, pavement infron of curb, temporary pavement for cross over, trim and fine grade , etc.
Answer:
This work will be incorporated by addendum.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Item 906.0210 - concrete 7.10. DOQ shows loactions at Bridges 712 and 713. The existing curbing at the approaches is slope face curb not straight face.
Answer:
New Items will be created by addendum.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify how the new deck joints, backwalls, and approach slabs for bridge 713 are paid for.
Answer:
The new deck joint is paid for under Item 823.1760. New Items will be added by addendum to address the backwalls and approach slabs.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify how the new granite curb and median on bridges 712 and 713 are paid for.
Answer:
Items will be added by addendum.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify how the existing granite curb and median(traffic separator) on Bridges 712 and 713 designated to be remove are paid for.
Answer:
Items will be added by addendum.
Date Asked: 10/24/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
There are notes on the plans stating that "All hollow areas and spalls shall be repaired using the partial depth patch repair and paid under item no. 818.0200 - portland cement concrete deck repairs (partial depth removal). These repairs are overhead repairs. The specification for 818.0200 states to use HP concrete. It will be very difficult to use HP concrete for partial overhead repairs. Usually overhead repairs are paid under item 817.2110.
Answer:
An Item will be added by addendum.
Date Asked: 10/22/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
The completion date of the project is 6/7/19 for Bridge 849 and 10/11/19 for the remaining bridges. Due to the size of the project and phasing, the department should consider extending the project into 2020. If not the contractor will be forced to carry liquated damages into their bid which will be passed onto RIDOT.
Answer:
The completion date has been reviewed, and determined to remain.
Date Asked: 10/22/2018 Date Answered: 10/29/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify what are the limits of the existing steel painting.
Answer:
Limits of existing steel painting are shown on Plan Sheets 25, 79 and 80.
Date Asked: 10/10/2018 Date Answered: 10/11/2018
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Do steel repairs have to be completed by AISC certified fabricator and erector.
Answer:
Yes, steel repairs have to be completed by an AISC certified fabricator and erector. Refer to Structural Steel Note 2 on General Bridge Notes Sheet 2 of 3 for fabricator certification. A note will be added by addendum for erector certification.