Questions and Answers For:

Statewide Bridge Repairs C-4 2019-CB-011

Please Note: If this is the first time accessing our system on our new web site, you will be required to reset your password.

The ask question function is now disabled;
please call 401-222-2495 x 4100 with any new questions.

Date Asked: 01/31/2019 Date Answered: 02/01/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify if all the shielding needs to be installed prior to starting work or can shielding be placed in the phase being worked on.
Answer:
This can be determined by the Contractor's means and methods. Please note that this item is a required submittal that must be reviewed and approved by RIDOT and Amtrak.
Date Asked: 01/31/2019 Date Answered: 01/31/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Sheet 72 Detail showing the close and seal end of the shielding to contain demolition debris. Please clarify the pay limits if the vertical portion for closing the interior bay shielding is paid by the square foot.
Answer:
The vertical portion labeled “Close off and seal end of shielding to contain debris” shown on the detail titled “Typical Section at Abutments for Backwall, Deck Edge and Approach Slab Rebuild” is not to be measured for payment. Closures are considered to be incidental to the work. The horizontal pay limits are as shown on the individual bridge plans and the vertical limits (at fascia overhangs and return walls) are as detailed on Sheet 72.
Date Asked: 01/30/2019 Date Answered: 01/30/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
On Bridge 772 since the pavement removal on the deck is full depth and new waterproofing is being placed, the final paving on bridge and approaches will be completed within the phases.
Answer:
This will be clarified in an addendum.
Date Asked: 01/30/2019 Date Answered: 01/30/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Item 803.0400 - clean beam seats. Is the 2 ea for bridge 243 per each abutment?
Answer:
This will be clarified in an addendum.
Date Asked: 01/30/2019 Date Answered: 01/30/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
On sheet 20 - full depth construction over the approach slabs show Modified 9.5 not Class 9.5. I am still confused where the class 9.5 is placed.
Answer:
The detail will be clarified in an addendum.
Date Asked: 01/29/2019 Date Answered: 01/30/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Item 401.0300 includes 30 tons for Bridge 243. Please clarify where this quantity is used.
Answer:
This quantity accounts for the areas of full-depth pavement removal and replacement on the bridge approaches above the approach slab reconstruction.
Date Asked: 01/29/2019 Date Answered: 01/30/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
sheet 20 - proposed abutment sections show 1 1/2" class 9.5 approach pavement. Should the detail say friction?
Answer:
The 1 1/2" class 9.5 approach pavement shown on the proposed abutment sections on Sheet 20 is intended to act as the friction course.
Date Asked: 01/29/2019 Date Answered: 01/30/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
How is the R & d granite curb on bridge and off bridge paid for?
Answer:
This will be clarified in an addendum.
Date Asked: 01/29/2019 Date Answered: 01/31/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
spec 410.9901 micro milling and filling rumble strip. The spec states to cold plane 1" deep. Usually the removal is 2". The pavement for the 1" deep ususally comes loose. Also is tack coat need for this item and how is it paid for?
Answer:
This will be clarified in an addendum.
Date Asked: 01/29/2019 Date Answered: 01/31/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Spec 402.9901 Friction Course states to use PG 64E-28 oil. Please confirm that the Department wants to use this special modiied oil with friction.
Answer:
Confirmed: PG-64E-28 is required when placing Friction Course.
Date Asked: 01/29/2019 Date Answered: 01/30/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify the sequence of construction for the paving on the bridge and approaches. Does the cold planning and paving get complete within each phase or does it get completed after all the phases are completed. If it is after all the phases are completed, the pavement on the new joints would have to be cold planned and paved to allow for a smooth transition.
Answer:
The intent is for cold planning and final paving to take place after all of the phases are completed. The DOQ includes additional pavement quantities to account for the “sacrificial” pavement that must be placed at the end of each phase, but will be removed under final cold planning & paving.
Date Asked: 01/24/2019 Date Answered: 01/25/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
WHO IS RESPOONSIBLE FOR THE AMTRAK PERMIT FEE?
Answer:
The Contractor shall be responsible for the Amtrak permit fee per standard specification 107.03.
Date Asked: 01/24/2019 Date Answered: 01/25/2019
Poster: Mike Sarrasin Company: John Rocchio Corporation
Question:
Is Railroad Protective Liability insurance required? If so, to what limits?
Answer:
Yes, Amtrak protective insurance is required. Limits shall be included in an addendum.
Date Asked: 01/24/2019 Date Answered: 01/24/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
iTEM 410.9901 - FILL RUMBLE STRIP WITH TEMPORARY PATCH. THIS SPEC DOES NOT CALL TO MILL(REMOVE) THE EXISTING RUMBLE STRIP. FILL THE EXISTING EXISTING RUMBLE STRIP WILL NOT WORK, THE TEMPRARY MIX WILL NOT LAST. THE EXISTING RUMBLE STRIP WILL NEED TO BE REMOVED PRIOR TO PLACING TEMPORARY MIX.
Answer:
This will be addressed in Addendum #1.
Date Asked: 01/24/2019 Date Answered: 01/24/2019
Poster: Mike Sarrasin Company: John Rocchio Corporation
Question:
Bid Item 016 410.9901 MICRO MILLING AND FILL RUMBLE STRIP WITH CLASS 12.5 HOT MIX ASPHALT. Sheet 073 and 074 show FRS - FILL RUMBLE STRIP WITH TEMPORARY PATCHING MATERIAL CODE 410.9901. Sheet 074 shows CUT RUMBLE STRIP DETAIL. The LEGEND: MPP calls for "CUT RUMBLE STRIP LEFT AND RIGHT SHOULDERS (NOT ON BRIDGE)." Page JS-19 calls for the rumble strips to be filled in by hand. Are the existing rumble strips removed and filled or hand patched? There is no item for cutting new rumble strips.
Answer:
This will be addressed in Addendum #1.
Date Asked: 01/23/2019 Date Answered: 01/24/2019
Poster: Mike Sarrasin Company: John Rocchio Corporation
Question:
There are several items where the quantity in the RFQ is different from the quantity in the Distribution of Quantities.
Answer:
This question will be addressed in Addendum #1. The addendum will include, but may not be limited to, a re-issued Distribution of Quantities.
Date Asked: 01/21/2019 Date Answered: 01/23/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
839.0100 INCLUDES 540 SY FOR BRIDGE NO. 243 AND 839.0100 INCLUDES 620 SY FOR BRIDGE 243. PLEASE CLARIFY WHICH ITEM WILL BE USED TO PAY FOR THE MILLING ON THE BRIDGE.
Answer:
This question will be addressed in an addendum. The addendum will include, but may not be limited to, a re-issued Distribution of Quantities.
Date Asked: 01/21/2019 Date Answered: 01/23/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
ITEMS 817.9901 AND 817.9902 ARE PAID BY THE SF. TYPICAL THESE ITEMS ARE PAID BY THE CF BEACUSE THE DEPTH OF THE DETERIORATED CONCRETE IS UNKOWN. IF THE ITEMS ARE TO BE PAID BY THE SF, PLEASE PROVIDE A DEPTH THAT SHOULD BE CARRIED FOR BIDDING PURPOSE.
Answer:
The depth of repairs shall be sufficient to expose a bonding surface of sound material per the Standard Specifications.
Date Asked: 01/21/2019 Date Answered: 01/22/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Please clarify if the contract number is 2018-CB-011 or 2019-CB-011. The request for quote states 2019-CB-011 and the contract hard copy state 2018-CB-011.
Answer:
The correct number is 2019-CB-011
Date Asked: 01/17/2019 Date Answered: 01/17/2019
Poster: Gary Garzone Company: Contracts
Question:
The Advertising CD has no Quest Lite Bid file. When will it be available ?
Answer:
The Quest Lite Bid file will be available to download from the State Purchasing web-site once the First Addendum is issued.