Date Asked: 06/20/2019 | Date Answered: 06/21/2019 |
Poster: Lee Taylor | Company: D'Ambra Const. Co., Inc. |
Question:
Addendum #2 will not import to Quest. Please check. |
|
Answer:
Addendum #3 will need to be posted to produce a new Quest Lite file. |
Date Asked: 06/11/2019 | Date Answered: 06/12/2019 |
Poster: Gary Garzone | Company: Contracts |
Question:
For clarification, when is work allowable for Group 1? |
|
Answer:
As updated by Addendum 1, the allowable dates for Group 1 are April 16, 2020 to December 3, 2020. |
Date Asked: 06/06/2019 | Date Answered: 06/06/2019 |
Poster: Dan Kelley | Company: Aetna Bridge Company |
Question:
Contract Specific page CS-5 states the Group 1 bridge work must be performed from April 16, 2020 to November 20, 2020. Appendix B, Stormwater Pollution Prevention Plan, page 5, states the estimated Group 1 bridge work is from 4/16/19 to 11/20/19. If the CS pages are correct then no contract work would occur prior to 4/16/20. Please confirm which dates are correct for the Group 1 bridges. |
|
Answer:
The correct dates are April 16, 2020 to November 20, 2020. Page 5 of the SWPPP will be revised by addendum. |
Date Asked: 06/04/2019 | Date Answered: 06/06/2019 |
Poster: Mike Sarrasin | Company: John Rocchio Corporation |
Question:
Item 810.0702 WELDED WIRE FABRIC (GALVANIZED); The mesh is not shown in the plans. What size is the mesh and where is this used? |
|
Answer:
Welded wire fabric is to be used for the concrete repairs as shown on Sheet 7 of the Plans. |
Date Asked: 06/04/2019 | Date Answered: 06/06/2019 |
Poster: Mike Sarrasin | Company: John Rocchio Corporation |
Question:
There is no item for water control at BABBITT FARM BRIDGE NO. 000901 and there are multiple items of work at this location. Please provide an item for water control. |
|
Answer:
Per General Note 9 on Sheet 6, water control shall be considered incidental to the work except where pay items are provided for specific bridges. Water control pay items are provided for Bridge Nos. 4 and 1157, and water control shall be considered incidental for all other bridges. |
Date Asked: 06/03/2019 | Date Answered: 06/06/2019 |
Poster: Mike Sarrasin | Company: John Rocchio Corporation |
Question:
Bid Item 039 - 808.1501; Please clarify the quantity of deck replacement. The Distribution of Quantities shows 2 cy each at Bridges No. 076801 and 099201. Sheet 36 shows deck repairs at Bridge No. 099201. |
|
Answer:
The quantities will be revised by addendum. |
Date Asked: 06/03/2019 | Date Answered: 06/06/2019 |
Poster: Mike Sarrasin | Company: John Rocchio Corporation |
Question:
Please clarify the limits of concrete removal at Bridge No. 076801. Are the approach slabs, deck and backwalls removed and replaced full width? |
|
Answer:
The work shown in the sections on Sheet 31 of the Plans are full width between concrete barriers but do not included the barrier width. |