Questions and Answers For:

Bridge Group 18B 2019-CB-061

Please Note: If this is the first time accessing our system on our new web site, you will be required to reset your password.

The ask question function is now disabled;
please call 401-563-4100 with any new questions.

Date Asked: 06/20/2019 Date Answered: 06/21/2019
Poster: Lee Taylor Company: D'Ambra Const. Co., Inc.
Question:
Addendum #2 will not import to Quest. Please check.
Answer:
Addendum #3 will need to be posted to produce a new Quest Lite file.
Date Asked: 06/11/2019 Date Answered: 06/12/2019
Poster: Gary Garzone Company: Contracts
Question:
For clarification, when is work allowable for Group 1?
Answer:
As updated by Addendum 1, the allowable dates for Group 1 are April 16, 2020 to December 3, 2020.
Date Asked: 06/06/2019 Date Answered: 06/06/2019
Poster: Dan Kelley Company: Aetna Bridge Company
Question:
Contract Specific page CS-5 states the Group 1 bridge work must be performed from April 16, 2020 to November 20, 2020. Appendix B, Stormwater Pollution Prevention Plan, page 5, states the estimated Group 1 bridge work is from 4/16/19 to 11/20/19. If the CS pages are correct then no contract work would occur prior to 4/16/20. Please confirm which dates are correct for the Group 1 bridges.
Answer:
The correct dates are April 16, 2020 to November 20, 2020. Page 5 of the SWPPP will be revised by addendum.
Date Asked: 06/04/2019 Date Answered: 06/06/2019
Poster: Mike Sarrasin Company: John Rocchio Corporation
Question:
Item 810.0702 WELDED WIRE FABRIC (GALVANIZED); The mesh is not shown in the plans. What size is the mesh and where is this used?
Answer:
Welded wire fabric is to be used for the concrete repairs as shown on Sheet 7 of the Plans.
Date Asked: 06/04/2019 Date Answered: 06/06/2019
Poster: Mike Sarrasin Company: John Rocchio Corporation
Question:
There is no item for water control at BABBITT FARM BRIDGE NO. 000901 and there are multiple items of work at this location. Please provide an item for water control.
Answer:
Per General Note 9 on Sheet 6, water control shall be considered incidental to the work except where pay items are provided for specific bridges. Water control pay items are provided for Bridge Nos. 4 and 1157, and water control shall be considered incidental for all other bridges.
Date Asked: 06/03/2019 Date Answered: 06/06/2019
Poster: Mike Sarrasin Company: John Rocchio Corporation
Question:
Bid Item 039 - 808.1501; Please clarify the quantity of deck replacement. The Distribution of Quantities shows 2 cy each at Bridges No. 076801 and 099201. Sheet 36 shows deck repairs at Bridge No. 099201.
Answer:
The quantities will be revised by addendum.
Date Asked: 06/03/2019 Date Answered: 06/06/2019
Poster: Mike Sarrasin Company: John Rocchio Corporation
Question:
Please clarify the limits of concrete removal at Bridge No. 076801. Are the approach slabs, deck and backwalls removed and replaced full width?
Answer:
The work shown in the sections on Sheet 31 of the Plans are full width between concrete barriers but do not included the barrier width.