Questions and Answers For:

Mileage Based Exit Renumbering 2019-CT-060

Please Note: If this is the first time accessing our system on our new web site, you will be required to reset your password.

The ask question function is now disabled;
please call 401-563-4100 with any new questions.

Date Asked: 08/01/2019 Date Answered: 08/07/2019
Poster: Michelle Ingram Company: Liddell Brothers, Inc.
Question:
Within the Job Specific Specifications on Page JS-6 Section 108.1000 Prosecution and Progress the Department has the Interim Completion Date as December 20, 2019 with the Substantial Completion Date of February 28, 2020. After contract award, the Overhead Sign Structure items (T17.0202, T17.0203, T17.0204 and T17.0210) within this project will require a lengthy submittal process of 8 to 12 weeks as well as a lengthy fabrication lead time after approval of 12 to 14 weeks. That said we feel the December 20, 2019 and February 28, 2020 dates are not achievable for this projects scope. We respectfully request that the Department consider moving the dates out to an Interim date of March 20, 2020 with the Substantial Completion Date of May 31, 2020.
Answer:
The substantial completion date will be changed in Addendum No. 1