Date Asked: 06/10/2020 Date Answered: 06/15/2020
Poster: Lee Taylor Company: D'Ambra Const. Co., Inc.
Question:
Item #41 - Maintenance and movement of traffic protection was not given a minimum bid price as is usually the case. Please clarify if this is correct.
Answer:
This will be answered in the Addendum
Date Asked: 06/10/2020 Date Answered: 06/15/2020
Poster: Lee Taylor Company: D'Ambra Const. Co., Inc.
Question:
Item #10 - was not given a minimum bid price as per the existing blue book specification. The job specific description of this item for this project is written to describe a daily penalty if maintenance is not performed. Therefore there should not be a lump sum bid item for this if the maintenance is to be performed as part of other items? Please clarify the intent of Item #10.
Answer:
This will be answered in the Addendum