Date Asked: 10/29/2020 | Date Answered: 10/30/2020 |
Poster: Raymond Giordano | Company: Cardi Corporation |
Question:
Page CS-4 paragraph I. states "The RIDOT expects the Contractor to work year-round. There is no winter shutdown for this project." Since every phase shown on the traffic control plans requires pavement to be placed prior to proceeding to the next phase, and asphalt plants are not open in the winter, it will not be possible to complete any work during the winter. Please reconsider this requirement and include a winter shutdown. |
|
Answer:
This project will have no winter shutdown. The contractor shall plan activities according to Blue Book and Project Specifications accordingly. |