Questions and Answers For:

Professional Consultant Services and ITS Technical Support to the RIDOT TMC 7598895

Please Note: If this is the first time accessing our system on our new web site, you will be required to reset your password.

The ask question function is now disabled;
please call 401-563-4100 with any new questions.

Date Asked: 08/07/2019 Date Answered: 08/14/2019
Poster: Daniel Herstine Company: Jacobs
Question:
Please clarify the “Current Workload” requirement on page 17 to list “all projects involving ITS that the firm is currently (and pending, if applicable) contracted to perform”. It can be challenging to list “all projects involving ITS” with large global companies such as ours. Is it acceptable to only include ITS contracts involving our key proposed staff?
Answer:
In the listing of projects included in the Proposal in response to the Current Workload stipulations on Page 17, it is acceptable for Respondents to exclude/omit projects for which no member of the proposed project team has or will have any involvement.