Date Asked: 01/21/2021 Date Answered: 01/22/2021
Poster: Jeff Lewis Company: Garofalo
Question:
On the debarment form, there is no line for signature. Is there a page missing?
Answer:
It is acceptable to sign and date the bottom of the form.
Date Asked: 01/13/2021 Date Answered: 01/19/2021
Poster: Dawn Connelly Company: Green International Affiliates, Inc.
Question:
Is it permissible for the Project Manager to also serve as the Lead Design Manager?
Answer:
The same person may be assigned as both the Project Manager and Lead Design Manager.