Questions and Answers For:

Pawtucket Salt Storage Facility (Solicitation Documents Available Online at ridop.ri.gov Bid Number 7642824) 2021-CM-047

Please Note: If this is the first time accessing our system on our new web site, you will be required to reset your password.

Date Asked: 06/11/2021
Poster: Donna Wigley Company: Tower Construction Corp
Question:
Are we to provide & install furring over the girts to install the horizontal wall siding?
Date Asked: 06/10/2021
Poster: Donna Wigley Company: Tower Construction Corp
Question:
This project has a November 2021 completion date. At this time the pre-engineered metal building manufacturers will not be able to deliver the building until 2022. Will DOT be able to work with the contractor on the building delivery date?
Date Asked: 06/10/2021
Poster: Donna Wigley Company: Tower Construction Corp
Question:
Are testing costs the responsibility of the owner?
Date Asked: 06/10/2021
Poster: Donna Wigley Company: Tower Construction Corp
Question:
Is a temporary owner’s trailer required?
Date Asked: 06/10/2021
Poster: Donna Wigley Company: Tower Construction Corp
Question:
Is the field applied rust inhibitor to be applied to all structural steel surfaces on the interior of the building? Can you provide a specification for the rust inhibitor?
Date Asked: 06/09/2021
Poster: Mike Montle Company: Martone Serive Company
Question:
Based on bid date, award and all the requirements of this project with regards to contaminated soil, has the construction completion date been realistically evaluated? Liquidated damages are at $1,200 per day and the hygienst are saying the schedule will not be met?
Date Asked: 06/09/2021
Poster: Mike Montle Company: Martone Serive Company
Question:
Can the RIDEM Remedial Approval letter be provided prior to bid?
Date Asked: 06/09/2021
Poster: Mike Montle Company: Martone Serive Company
Question:
Spec section 300120 refers to the Construction Soil Management Plan (CSMP) is this going to be provided prior to bid?
Date Asked: 06/09/2021
Poster: Mike Montle Company: Martone Serive Company
Question:
Is there a GEO Tech report available for this project?
Date Asked: 06/09/2021
Poster: Mike Montle Company: Martone Serive Company
Question:
Drawing A101 references "Landscaped area refer to civil drawings" please clarify as it appears there is no reference to Landscaping on civil drawings.
Date Asked: 06/09/2021
Poster: Mike Montle Company: Martone Serive Company
Question:
What is the floor drain requirements. Where is the piping going and what is the piping requirements? Is there a fuel water separator requirement?
Date Asked: 06/09/2021
Poster: Mike Montle Company: Martone Serive Company
Question:
Are any of the following building manufacturers acceptable substitutions: Metallic, Chief Industries, or American Building?
Date Asked: 06/08/2021
Poster: Matthew Jesus Company: Cardi Corp.
Question:
for the proposed precast catch basin std 4.4.0, what is the intentions for this structure. is there any piping that will be tied into this structure that is not shown on the plans? or will this structure act as a dry well and be maintained by RIDOT in the future?
Date Asked: 06/08/2021
Poster: Matthew Jesus Company: Cardi Corp.
Question:
is there an existing Remedial Action Work Plan available for review?
Date Asked: 06/08/2021
Poster: Matthew Jesus Company: Cardi Corp.
Question:
Are we able to use native "dry" contaminated soil as backfill under the proposed soil cap?
Date Asked: 06/08/2021
Poster: Matthew Jesus Company: Cardi Corp.
Question:
Are we able to stockpile excavated "dry" contaminated soil?