Park Avenue Railroad Bridge

Bridge CLOSED | Click for Details

  • RIDOT Centerville Road & Toll Gate Road Bridge Project
    Park Ave Railroad Bridge Demolition, Cranston RI
  • RIDOT Centerville Road & Toll Gate Road Bridge Project
    Park Ave Railroad Bridge Eastbound, Cranston RI
  • RIDOT Centerville Road & Toll Gate Road Bridge Project
    Park Ave Railroad Bridge Westbound, Cranston RI

Project Overview

We will completely replace the Park Avenue Railroad Bridge, which carries Park Avenue (Route 12) over Amtrak's Northeast Corridor between Elmwood Avenue (Route 1) and Wellington Avenue in Cranston. The bridge has been structurally deficient for many years and dates back to 1906.

The bridge was closed in mid-spring 2021 for demolition and reconstruction. RIPTA is running a free shuttle during the closure. We intend to reopen the bridge prior to the start of school in fall 2021.

To replace this bridge in as short a timeframe as possible, we are using early contractor involvement procurement method as well as accelerated bridge construction methods. Together, these steps will allow the Department to complete the project up to three months faster than using conventional methods.

PROJECT UPDATES | JUNE, 2021

Next week, overnight demolition of the wooden bridge deck is scheduled. As a reminder, the bridge remains closed to vehicles and pedestrians, with seven-day pedestrian access via a RIPTA shuttle from 6 a.m. to 10 p.m.

Click here for the latest lane closure information