Date Asked: 05/24/2018 | Date Answered: 05/29/2018 |
Poster: Anthony Mesiti | Company: Cardi Corporation |
Question:
THE SPECIFICATION STATES THAT THIS A STATE FUNDED PROJECT, BUT THE REQUIRED CONTRACT PROVISIONS - FEDERAL AID CONSTRUCTION CONTRACTS IS INCLUDED WITH THE CONTRACT DOCUMENTS. PLEASE CLARIDY IF THE FEDERAL AID RERQUIREMENTS APPLY TO THIS PROJECT. |
|
Answer:
The Federal Aid requirements do apply to this project. |
Date Asked: 05/24/2018 | Date Answered: 05/29/2018 |
Poster: Anthony Mesiti | Company: Cardi Corporation |
Question:
A GENERAL CONTRACTOR APPRENTICESHIP CERTIFICATION FORM WAS INCLUDED IN ADDENDUM NO.1. PLEASE CLARIFY IF THIS FORM NEEDS TO BE SUBMITTED WITH THE BID. |
|
Answer:
Yes, the General Contractor Apprenticeship Certification Form is required with the bid. |