Date Asked: 08/03/2018 | Date Answered: 08/06/2018 |
Poster: Joe Colapietro | Company: Cardi Corporation |
Question:
Will the job completion date be revised? The new TMP has reduced working hours compared to the original bid, and the completion date was moved from August to July 2019. This job is now being bid a month later, with decreased work hours and decreased days to completion. Please advise. |
|
Answer:
It is acknowledged that the completion date has changed however it will not be revised and will remain at July 31, 2019. Note that the allowable dates that the road can be closed for construction has been increased from the original bid package. The shop drawing review time has also been reduced to 21 days. |
Date Asked: 08/01/2018 | Date Answered: 08/03/2018 |
Poster: Lee Taylor | Company: D'Ambra Const. Co., Inc. |
Question:
There are a large amount of "Round up" or "Contingency" item quantities in the distribution of quantities item breakdowns. This project is being rebid due to mistakes made to the quantity breakdowns given the first time around. Is it possible to put out a project to bid with proper plans that show where the work is, and has corresponding bid quantities to match? This would help solve any future bidding irregularities. |
|
Answer:
The roundup and contingency items have been reviewed and considered appropriate when provided. |
Date Asked: 07/30/2018 | Date Answered: 08/03/2018 |
Poster: Joe Colapietro | Company: Cardi Corporation |
Question:
Trimming and Fine Grading includes a quantity of 846.92 SY for the purposes of "Rounding Up". This seems excessive, can this quantity be revised? |
|
Answer:
Roundup and contingency quantities have been reviewed and considered appropriate when provided. |
Date Asked: 07/30/2018 | Date Answered: 08/03/2018 |
Poster: Joe Colapietro | Company: Cardi Corporation |
Question:
How Will Dust control Be Paid? It is stated as being part of the Reclamation item, but the entire reclaimed area is also listed under Calcium and Water for dust control. Please advise. |
|
Answer:
The Job Specific for Item Code 406.9901 will be revised via addendum to clarify the basis of payment for water and calcium chloride for dust control under this item code. |