Date Asked: 04/27/2018 | Date Answered: 05/01/2018 |
Poster: James Hurley | Company: RoadSafe Traffic Systems |
Question:
Concerning item 922.0100 on the Limited Access Contract, the bid item list only calls for 1 SF of Temporary Construction Signs. Assuming this is an error, could this be changed? Also, seeing as these pavement marking contracts are being advertised much later than usual, will there be any flexibility with the completion dates? |
|
Answer:
Regarding Item 922.0100 Temporary Construction Signs Standard 29.1.0 and 27.1.1, an Addendum will be prepared to correct the quantity of 1 SF. Regarding the completion dates, the completion dates will not be changed. The completion dates have already been extended from the usual dates on previous contracts. |