Questions and Answers For:

Bridge Group 16B 2019-CB-068

Please Note: If this is the first time accessing our system on our new web site, you will be required to reset your password.

Date Asked: 09/20/2019
Poster: Dan Kelley Company: Aetna Bridge Company
Question:
Bridge 274 requires deck end reconstruction but does not have a site specific traffic plan. The TMP allows one lane of alternating traffic during weekdays only. To complete with work will require either phased construction with barrier or temporary traffic plates. Please advise.
Date Asked: 09/20/2019
Poster: Dan Kelley Company: Aetna Bridge Company
Question:
Job Specific Item 800.9901 Temporary Protective Shielding is not included as a bid item on the project. It appears JS Item 800.9902 Miscellaneous Bridge Repairs mistakenly replaced this item in the DOQ. Please clarify.
Date Asked: 09/20/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
ITEM 401.9902 REMOVE AND REPLACE OVERLAY AND WATERPROOFING FOR BRIDGE 274. NOTES ON SHEET 51 STATE THAT THE REMOVAL, REPLACEMENT AND WATERPROOFING ARE PAID ON DIFFERENT ITEMS. PLEASE CLARIFY.
Date Asked: 09/20/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
ietm 501.0103 bridge 83 calls for 7 cy. We calculate 45' x 1' x1' = 1.7 cy. Please clarify where the remaining quantity is located.
Date Asked: 09/20/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
item 202.0800 gravel borrow for bridge 83 - 20 cy. Please clarify where this item is used if the existing base is to remain.
Date Asked: 09/20/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
items 906.0110 and 906.0700 for bridge 232. Please clarify if the curb is replaced or removed and reset.
Date Asked: 09/17/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
926.9901 - PLEASE PROVIDE APPROVED TL-4 TRAFFIC BARRIERS.
Date Asked: 09/16/2019 Date Answered: 09/17/2019
Poster: Anthony Mesiti Company: Cardi Corporation
Question:
Sheet 57 note 6 states that replacement rebar is incidental to the repair item. The specs state that replacement rebar is paid on fore accounbt basis since it is unknown at bid time. please clarify.
Answer:
The replacement reinforcement shall be paid for by Force Account per the specification. The referenced note will be revised by Addendum.