Questions and Answers For:

2020 Paver Placed Elastomeric Surface Treatment C-1 2020-CR-011

Please Note: If this is the first time accessing our system on our new web site, you will be required to reset your password.

The ask question function is now disabled;
please call 401-563-4100 with any new questions.

Date Asked: 02/27/2020 Date Answered: 02/27/2020
Poster: Lee Taylor Company: D'Ambra Const. Co., Inc.
Question:
There is a 4% DBE requirement for this project. The list of bid items does not include many work items that are traditionally performed by R.I. DBE subcontractors. Item #11 - Supplemental price adjustments and #12 - Miscellaneous work are must bid items worth $125,000.0 value. will these items be considered for DBE participation, as it is possible that these could be performed by DBE subcontractors?
Answer:
The DBE requirement will remain 4% for this project and Items #11 and #12 can be considered for DBE participation.
Date Asked: 02/21/2020 Date Answered: 02/21/2020
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Please specify how much berm is to be included or make it a force account item. You are not providing any information to price other than when we are in the field it will be determined. We cannot price something we do not know the extent of.
Answer:
The cost of new berm will remain included in Items 401.9901 and 411.9902 and be installed as described on Page CS-3 Paragraph 4j. New berm will not be a force account item. It is recommended that bidders conduct a field review of each road in development of bid prices.
Date Asked: 02/20/2020 Date Answered: 02/21/2020
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Will a mobilization item be added to this contract?
Answer:
See Page CS-1 Paragraph 3c. a. Mobilization/Demobilization. There will be no separate pay item for Mobilization/ Demobilization and all such mobilization and demobilization shall be incidental to the work.
Date Asked: 02/20/2020 Date Answered: 02/21/2020
Poster: Joe Colapietro Company: Cardi Corporation
Question:
How are temporary signs and traffic control devices paid for?
Answer:
See Page CS-4 Paragraph 5. The costs of all maintenance and protection of traffic shall be included in the item for the construction operation being conducted. There shall be no separate item or payment for provision of construction signing, protective devices, nor for the maintenance and protection of traffic.
Date Asked: 02/20/2020 Date Answered: 02/21/2020
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Because Leveling is not a uniform depth please provide a separate item for tack with the expected sy for leveling.
Answer:
See Page CS-2 Paragraph 4e. Emulsion tack coat costs will be included in Item 401.4002 Class 4.75 for leveling.
Date Asked: 02/20/2020 Date Answered: 02/21/2020
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Please provide Quantity(SY) of Milling per location. The tons do not appear to match the SY when taking the average width and length of road provided in your chart. Please provide Further detail.
Answer:
The quantities listed in Table 1 are estimates. The cost of milling will be included in Items 401.9901 or 411.9902. Payment will be in accordance with the applicable job specifications.
Date Asked: 02/20/2020 Date Answered: 02/21/2020
Poster: Joe Colapietro Company: Cardi Corporation
Question:
Please provide quantities for the amount of berm to be replaced, and where.
Answer:
See Page CS-3 Paragraph 4j. The intent is to leave existing berm in place on the applicable roads. However, there are some sections of bituminous berm that are in poor condition and shall be replaced. The limits of new bituminous berm will be determined in the field by the Engineer. New berm will be paid for under Items 401.9901 or 411.9902.
Date Asked: 02/14/2020 Date Answered: 02/14/2020
Poster: Susan Cullen Company: J.H. Lynch & Sons, Inc.
Question:
Is there supposed to be plans on the disk for this project?
Answer:
There are no plans for this contract.