Little Compton Tiverton Paving

  • Reservoir Ave, Cranston RI
    Souza Road, Tiverton RI
  • Reservoir Ave, Cranston RI
    East Main Road, Little Compton RI

The Project

This project includes full pavement replacement, sidewalks, traffic signals and stormwater drainage upgrades at various locations In Tiverton and Little Compton.  No new signals are being installed on the project.

The areas to be improved are:

  • Tiverton
    • RI-77, Main Rd (Highland Rd to Evans Ave)
    • Riverside Dr (Rt 77 to RI-24)
    • Souza Rd (RI-138 to Fish Rd)
    • Bridgeport Rd (RI-177 to Highland Rd
    • Fish Rd (RI-177 to Sterling Dr)
    • Highland Rd (Bridgeport Rd to RI-77)
  • Little Compton
    • Meetinghouse Ln (Commons Rd to RI-77)
    • East Main Rd (Simmons Rd to Peckham Rd)
    • Simmons Rd (Willow Ave to East Main Rd)
    • Commons St (Meetinghouse Ln to South of Commons Rd)
    • South of Commons Rd (Brownell Rd to Commons St)

Project Schedule & Cost

  • Location: Little Compton, Tiverton
  • Start Construction: 2024
  • Finish Construction: 2025
  • Total Projected Cost: $30.1 Million
  • Detours Needed: Yes

PROJECT UPDATES | NOVEMBER, 2024

Tiverton motorists should expect alternating one-way traffic for curb, sidewalk and driveway construction on Route 77 (Main Road), from Bridgeport Road to Central Avenue, Monday and Wednesday-Friday from 7 a.m. to 5 p.m. Expect alternating lane closures to place asphalt for driveway aprons, on Highland Road, from Bridgeport Road to Main Road, Monday and Wednesday-Friday from 7 a.m. to 3 p.m.

Click here for the latest lane closure information