This project will consist of long-anticipated improvements to sidewalks on a section of North Kingstown's busiest commercial area on Post Road, from Camp Avenue to West Main Street, as well as on West Main Street itself, the main access to the village of Wickford (Post Road to Brown Street). More than two miles of roadway will be improved.
In addition to sidewalk improvements, we will upgrade drainage systems and build treatment units to capture pollutants in stormwater runoff. We will also add ADA-complaint wheelchair ramps and new pedestrian crossing signals. These roadways will be resurfaced after we complete work on the sidewalks.
![]() |
|
Next week, motorists should expect partial lane closures, narrowed lanes and frequent vehicle access in/out of the work zone for daytime pavement repairs and drainage improvements on Route 1 (Post Road), from Oakdale Avenue to Huling Road, Monday-Friday, from 9 a.m. to 3 p.m. The same operations will also be taking place on Route 1A, with alternating one-way traffic, narrowed lanes, shoulder closures and frequent vehicle access in/out of the work zone, from Brown Street to Post Road, Monday-Friday, from 9 a.m. to 3 p.m. |