Tower Hill Road Bridge & Paving

(Corridor-Tower Hill Road)
  • RIDOT Tower Hill Road - Route 1 Project
    Tower Hill Road - Bird's Eye
  • RIDOT Tower Hill Road - Route 1 Project
    Route 138 Westbound at Tower Hill Road - Route 1

The Project

The $35.8 million Tower Hill Road project includes replacement of the 55-year-old Tower Hill Road Bridge, carrying Tower Hill Road over Route 138 in North Kingstown, and resurfacing of 6.5 miles of Tower Hill Rd (US-1) from the Route 4 split in North Kingstown to the Oliver Stedman Government Center in South Kingstown.

Throughout the bridge’s replacement, we will utilize Accelerated Bridge Construction (ABC) methods and (SPMTs) Self-Propelled Modular Transporters. Additional work includes replacing the existing wheelchair ramps at the Bridgetown Road/Mooresfield Road intersection with ADA compliant ones, and improving stormwater treatment.


Project Schedule & Cost

  • Location: North Kingstown/South Kingstown
  • Start Construction: Winter 2023/Spring 2024
  • Finish Construction: Summer 2026
  • Total Projected Cost: $35.8 Million
  • Detours Needed: Yes

PROJECT UPDATES | JUNE, 2025

Overnight bridge, roadway, electric and general site work may involve temporary ramp closures, with detours in place, at the Routes 138 and 1 (Tower Hill Road) interchange and alternating lane closures along Route 1, from Shermantown Road to the Route 4 split, Sunday-Tuesday nights from 9 p.m. to 6 a.m. for barrier and guardrail connection installations at the bridge, new curbing and lighting. Daytime activities at the Routes 1 and 138 ramps, such as concrete form work, will also take place behind barrier, with frequent vehicle access in/out of work zone, Monday-Wednesday and Friday from 6:30 a.m. to 3 p.m.

Click here for the latest lane closure information